Save These Instructions This manual contains important instructions that must be closely followed during installation of this unit to maintain compliance with…
The highly-versatile Vertiv™ VR provides an organized, secure, controlled environment in a single system for sensitive electronic equipment. Table 2.1 below …
Vertiv™ VR assembled rack • Door and side-panel keys • (50) M6 cage nuts and M6 screws • Baying hardware • Edge grommet • Cage-nut install tool • T30 extension…
3.1 Equipment Inspection Upon receiving a Vertiv™ VR rack system, inspect the packaging for any signs of mishandling or damage. If any damage is noted, notify…
Upon receiving a Vertiv™ VR rack system, inspect the packaging for any signs of mishandling or damage. If any damage is noted, notify your local Vertiv™…
Before unloading, note the weight of the model in Table 2.1 on page 3 . The following tools/equipment are required to un-pack and move the rack: • pallet jack…
When planning the position and location of the rack, refer to Figure 3.3 below , for the required clearances for installation and service of the rack and…
Once your rack is in its final location, refer to the following procedures to install accessories, adjust components, and load equipment into the rack. The…
Rack doors are removable for convenience when installing or maintaining equipment. The front door is also reversible, so that the single door may be opened in…
1. Remove the Phillips-head bolt from the swing-handle retainer on the inside of the door. 2. Tilt the handle outward and lift up to remove it from the door.…
The rack uses dual split-side panels fashioned from sheet metal. Both panels rest on a frame member and are secured to the frame by a slam latch. The locking…
The rack uses a tool-less, removable top panel for simple removal and replacement. To remove the top panel: 1. Pull the pin located in the front of the rack.…
1. Press edge guard to the top-cover cut outs by pressing along the edge of the cut out opening as shown in the following figure. 2. Trim excess edge guard…
4.6 Positioning and Attaching Frontand Rear-Mount 19-in. EIA Rails Frontand rear-mount, 19-in., EIA rails are installed in racks at the factory at 29.13 in.…
Power distribution units may be mounted on the rails or attached to mounting brackets in the rack. Two PDU mounting brackets are standard in each rack. They…
Two or more racks of the same height can be bayed with the supplied baying brackets. The brackets have three hole locations (shown in Figure 4.12 on the facing…
WARNING! Each rack must have its own protective-earth conductor. Do not daisy-chain the protective-earth circuit using the multiple protective-earthing…
WARNING! To prevent the rack from tipping over, secure the rack to the floor before installing equipment. Once in place at the desired location, install…
The rack requires no special maintenance. Clean the rack periodically, or more frequently if the air in the vicinity is not filtered for particulates. Clean…