Modular Battery Cabinet Installation Up to 6 Battery Strings GVSMODBC6 6/2019 www.schneider-electric.com
Modular Battery Cabinet Important Safety Instructions — SAVE THESE INSTRUCTIONS Read these instructions carefully and look at the equipment to become familiar…
NOTICE HAZARD OF EQUIPMENT DAMAGE Refer to the UPS installation manual for detailed specifications for the UPS system. Failure to follow these instructions can…
Installation Kit 0H-9330 Part Used in Number of units Baying cover Interconnect Modular Battery Cabinet 1 and the Adjacent UPS with Internal Batteries, page…
Modular Battery Cabinet Installation Procedure Modular Battery Cabinets and Adjacent UPS Rated for Maximum 50 kW Modular Battery Cabinets and Remote UPS Rated…
Modular Battery Cabinet Prepare for Installation 1. Remove the front panel. 2. Remove the upper plate. 3. Remove the transparent plate. 4. Remove the top…
1. Remove the conduit box from the rear of the modular battery cabinet(s). Rear View of the Modular Battery Cabinet 2. Remove the top or bottom gland plate…
Modular Battery Cabinet Prepare Modular Battery Cabinet 1 for Signal Cables 1. Remove the gland plates and the brush plates from the rear of modular battery…
1. Mount the rear anchor(s) to the floor. Use appropriate hardware for the floor type – the hole diameter in the rear anchor is ø14 mm. Use the rear…
Modular Battery Cabinet Interconnect Modular Battery Cabinet 1 and the Adjacent UPS with Internal Batteries 1. Push modular battery cabinet 1 and the UPS into…
1. Push the UPS into place. 2. Install the three interconnection clamps on modular battery cabinet 1. Rear View of Modular Battery Cabinet 1 24 990-91263-001
Modular Battery Cabinet Interconnect the Modular Battery Cabinets 1. Push the modular battery cabinets into place. For seismic anchoring, ensure that the rear…
NOTICE RISK OF EQUIPMENT DAMAGE Only connect the DC cables from battery breaker to battery breaker in installations with a UPS rated for maximum 50 kW. For…
Modular Battery Cabinet Connect the Power Cables for a UPS Rated over 50 kW NOTICE RISK OF EQUIPMENT DAMAGE For installations with a UPS rated over 50 kW, the…
1. Assign an ID to each modular battery cabinet with the switch below the battery breaker. Set the IDs according to the installation overview images in…
The safety labels on your product are in English and French. Sheets with translated safety labels are provided with your product. 1. Find the sheets with…
Modular Battery Cabinet Final Installation DANGER HAZARD OF ELECTRIC SHOCK, EXPLOSION, OR ARC FLASH Batteries can present a risk of electric shock and high…